Lead Time/Look Back
Time:
It is the time
where we can look back for the execution of the Job in the previous run where
we can post the requirements if they are met.
·
Lead time varies from 0
to 99.
· 0 indicates no lead
time is to be considered when satisfying this job’s requirements.
·
98 maximum lead time value is 98 hours.
·
99 Each predecessor job
must complete normally while this job is in the request queue.
This is a special case, even though it is
equivalent to zero lead time. Because, the requirement is never to be
considered as already satisfied when the job enters the queues.
What is Lead Time?
What are Look-back issues?
Example
of a Look-back issue.
Very
often, there is too large a time-gap that elapses between a predecessor job A’s
completion, and its dependent B’s starting out. When B is brought into the
REQ(Request) Queue, if A’s completion doesn’t fall in the Look-back(Lead-time)
window, B keeps waiting in the REQ Queue. These are called Look-back issues.
CA-7 Look-back issues generally happen in the Production Environment, generally
due to delays in Batch Cycle, holidays etc.
Lead-Time
could take several values.
00-No
special consideration for the amount of
time elapsed, between the pred-job and dependent job’s runs.
99-The
requirement is never to be considered as already satisfied, when the job enters
the Queue.
nn-Since,
the last run of the job, each predecessor job must have run with in the last nn
hours. Values for run may be from 1 to 98.
what exactly i can say of lead time ???
ReplyDelete